Combining Two Apartments in NYC: Approvals and Cost

The apartment next door is coming up for sale, and you have been wanting another bedroom for years. Buying it and opening the wall between the two can be the easiest way to get a bigger home in Manhattan without leaving a building and a block you like. Plenty of owners do exactly that, often after searching for a larger place and finding nothing that fits.

This article walks through what a combination actually involves: what the building and the city have to approve, how a co-op differs from a condo, what the work costs and how long it takes, and the costs that sit outside the construction budget.

Two approvals, the building’s and the city’s

Before anything else, both apartments have to belong to you. Then the building has its say. In a co-op the board must approve the combination, and its reviewing architect will go through the plans the same way it would for any renovation, usually in a few rounds of comments. Many buildings have approved combinations before and have a routine for them. Others are cautious, especially about stairs between floors or anything structural. If you are serious about buying, ask the managing agent before you sign whether the building has allowed combinations and on what terms.

The city’s part is simpler than many people expect. Under a long-standing Department of Buildings policy, most combinations do not need a new certificate of occupancy, the document that records how a building may be used. The work is filed as an ordinary alteration and closes with a letter of completion, as long as it meets a short list of conditions: the apartments are on the same floor, or on two floors joined by an inside stair; the combined home has no more rooms than the two had together; every room keeps its light and air; the building’s stairs, corridors and exits stay as they are; and the second kitchen is removed. A combination that falls outside these conditions needs the longer filing that does change the certificate of occupancy. Your architect decides which path applies before anything is drawn.

 

Emptied galley kitchen in a pre-war apartment with capped sink, gas and range hood connections and outlets left on freshly plastered walls, the second kitchen removed

A co-op and a condo get there differently

In a co-op you own shares, so a combination is mostly a matter of the board’s consent. If you want the bit of public hallway between your two doors, co-ops often sell it by issuing you additional shares. Brokers and lawyers who handle these deals describe that as routine.

A condo is different because each apartment is its own piece of real estate with its own tax lot, the city’s record of it as a separate property for taxes. Before the city will approve the plans, your architect has to get a temporary tax number for the combined apartment from the Department of Finance, and after the work is finished the two lots are formally merged into one. The hallway is harder too: a condo’s shares of common space are meant to be fixed, so the building more often licenses that space to you than sells it, and a license can be withdrawn later. And in a building that has both kinds of apartments, a co-op unit and a condo unit cannot be merged into one legal home, even when they share a wall.

What it costs

The range is wide because “combining” can mean very different jobs. At the small end, keeping both layouts, cutting a doorway and taking out the extra kitchen can come in under $10,000 plus the filing. Few people stop there, because two separate layouts rarely work as one home. Most combinations become a full renovation of both apartments, and New York architects and contractors who do this work tend to plan $300 to $500 per square foot for a combination on one floor, and around $600 for one that joins two floors.

Joining two floors costs more for a plain reason: someone has to cut an opening in the concrete floor, add steel to carry it, and build a stair, with a structural engineer and extra inspections along the way. A single floor usually means opening a wall that holds nothing up. One published Murray Hill example shows the middle of the range: two side-by-side units combined into one home, with a new kitchen, bath, bedroom, laundry, wiring, plumbing and floors, for $300,000 and 22 weeks of construction.

As for time, contractors who do these projects put five to six months into design, board review and filing, and five to seven months into construction. Work runs longer than a single renovation because two apartments are being rebuilt and tied together at once.

The costs outside the construction budget

The renovation estimate is only part of the money. For most of a year you carry two apartments you cannot fully use: two sets of maintenance or common charges, any mortgage payments, and often rent somewhere else while the work goes on.

After the work is done, the maintenance on the combined apartment is set by the building and is not always the sum of the two old charges; sometimes it is more. Ask the managing agent what the combined charge will be before you commit to buying.

Financing also takes planning. Fewer lenders will finance a combination, and the ones that do often appraise each apartment separately and then the two together. A New York real estate lawyer describes a client whose existing loan treated the combination itself as a breach, so if either apartment carries a mortgage, have your lawyer confirm that combining them is allowed under the loan before work begins.

 

Architect resting his hand on the shared wall while talking with an owner in the empty apartment next door

 

Where to start

 

The order that avoids wasted money is the reverse of what most people do. Before you make an offer on the neighbor’s apartment, have an architect and a contractor walk both units. They can tell you whether the floors and ceilings line up, where the building’s main pipes (the risers that run up through every floor) and gas lines are, whether a bathroom can go where you want it given the building’s rules about putting a bathroom or kitchen over someone’s bedroom below, and what the job is likely to cost. Then ask the building how it handles combinations. With what the architect, the contractor and the building tell you, you know what you are buying before you buy it.

Is a combined apartment worth more than the two apartments separately?

Often, yes. Larger apartments are scarce in Manhattan and tend to sell for more per square foot, so a well-planned combination can be worth more than the two units were on their own. The gain is largest when the result reads as one home that was always one home. A plain doorway between two otherwise unchanged apartments adds the least, and a leftover second kitchen is the clearest sign to a buyer that the home used to be two.

Can I keep the second kitchen?

Not as a kitchen. The city's rules for combinations require the second kitchen to be taken out and its connections capped. They also allow the plans to reuse those connections for something else, such as a washer and dryer, a bar sink or a new bathroom, if that is shown on the approved drawings. Many owners turn the old kitchen into exactly that.

Do I need an architect to combine two apartments?

Yes. The filing with the Department of Buildings has to be prepared by a registered architect or professional engineer, who also signs off on the finished work so the city can issue the letter of completion.